| Digging the foundations for the tower. |
| Putting the re-bar reinforcing cage in place to strengthen the foundation. |
| Pouring the concrete. |
| Leveling the foundation. |
| Done! |
| Welding the tower for the solar pump. |
| Painting the legs of the tank tower. |
| Getting all the parts near the foundation. |
| Erecting the tank tower. |
| Welding everything together. |
| Pouring the foundation for the second tower. |
| Making a platform on top of the tower to be able to work on the second one. |